Sancon provided Project Management services to oversee the detailed design for the disconnection, relocation and reinstatement of a 200-man camp approx 5km away. The move was required due to the close proximity of an ever expanding Tailings Storage Facility. The entire relocation was implemented in a 10-week period.
The new facility included:
- 11kV/415V power infrastructure
- potable water
- kitchen
- dry mess facilities
- wet mess facilities
- future expansion to 1200-man camp
- laundries
- sewerage
- landscaping
- reticulation
- fencing
- telephones
- TV
- pool
- sporting facilities
- gym
- internet/quiet room
- admin offices
- lockers
- access roads; and
- Parking
The old site was successfully rehabilitated. All electrical work for the expansion of the new camp to 1200 beds.